Dubai's handover pipeline, 2026–2029: 362,636 homes on the register

How many homes are scheduled to complete in Dubai each year to 2029, how far along they are, how many 2026 dates have already slipped, and which areas carry the load.

Published · Updated · Data to · Peak Trust Research

Key figures

  • As of 4 October 2026, DLD's project register listed 362,636 homes in 1,340 open projects scheduled to complete in Dubai between 2026 and 2029, according to Peak Trust analysis of DLD records.
  • Dubai's project register showed 85,375 homes scheduled for completion in 2026, 104,339 in 2027, 107,484 in 2028 and 65,438 in 2029, as of 4 October 2026.
  • As of 4 October 2026, 145 open Dubai projects with 41,825 homes had passed a scheduled January–September 2026 completion date, and were on average 56% complete, weighted by homes.
  • Only 17,146 of the 85,375 homes scheduled to complete in Dubai in 2026 were in projects recorded as at least 80% complete in October 2026.
  • Of the 104,339 homes scheduled for completion in Dubai in 2027, 57,036 were in projects still recorded at 0% construction in October 2026.

DLD's project register lists 362,636 homes due to complete in Dubai between 2026 and 2029. The peak is 2027 and 2028, at just over 100,000 a year. A date on the register isn't a delivery, though. By early October half the homes due in 2026 had already missed their date, and more than half of the 2027 homes were in projects recorded at 0% construction.

The headline total matters less than three things underneath it: how far along each year's supply is, how much is already late, and which areas take the load.

All figures come from DLD's project register as loaded on 4 October 2026, for projects that are neither finished nor cancelled. "Homes" means apartments plus villas as recorded for each project. Construction percentages are the figures on the register, and we treat the 19 values outside 0–100% as unknown. "Scheduled" means the completion date on the register, which developers update and which often moves.

How many homes are scheduled to complete each year?

Table: open projects and homes on the DLD register by scheduled completion year, with recorded construction progress, as of 4 October 2026. Progress is weighted by homes. Source: DLD project register, Peak Trust Research.

Scheduled completion Projects Homes Apartments Villas Construction recorded (home-weighted) Projects not started Homes in 80%+ complete projects
2025 or earlier, still open 148 40,003 n/a n/a n/a 1 n/a
2026 265 85,375 82,135 3,240 60% 2 17,146
2027 430 104,339 98,780 5,559 7% 159 99
2028 426 107,484 93,791 13,693 3% 145 0
2029 219 65,438 59,375 6,063 1% 60 0
2030 77 37,910 29,013 8,897 0% 6 0
No date on the register 211 62,822 58,842 3,980 19% 17 916

Of the 148 open projects dated 2025 or earlier, 109 (25,800 homes) were due in 2025 and were on average 53% complete. The rest form a tail of older dates going back to 2010. This count includes one frozen project of 108 homes. Our Developer Outlook leaves frozen projects out, which is why it counts 147 projects and 39,895 homes rather than 148 and 40,003.

Apartments are 92% of the 2026–2029 pipeline, 334,081 of 362,636 homes. Villas grow in the later years, with 13,693 of the homes due in 2028.

How much of 2026 is actually built?

Less than the headline suggests. Of the 85,375 homes with a 2026 date, only 17,146 were in projects at 80% or more. Another 33,586 were at 50–79%.

Table: homes on the DLD register by scheduled completion year and recorded construction progress, as of 4 October 2026. Source: DLD project register, Peak Trust Research.

Construction recorded 2026 2027 2028 2029
80–100% 17,146 99 0 0
50–79% 33,586 2,705 0 0
20–49% 17,608 10,266 3,826 293
1–19% 3,683 34,209 40,952 22,533
0% 521 57,036 62,559 41,580
Not recorded 12,831 24 147 1,032
Total 85,375 104,339 107,484 65,438

Slippage is already visible. As of 4 October 2026, 145 projects with 41,825 homes had passed a January–September 2026 completion date and were still open, on average 56% complete (weighted by homes). Only 5,832 of those homes were in projects at 80% or more. The 120 projects due in October–December 2026, with 43,550 homes, averaged 64% on the same basis.

The register shows the same gap from the delivery side. Of the homes in projects dated January–June 2026, 22,975 (41%) were in projects recorded as finished by early October, and 33,421 were still open.

Completions are rising all the same, because older late projects are finishing too. The register recorded 33,499 homes completed in Q2 2026 and 33,566 in Q3, against 31,078 in the whole of 2025. Many of those projects carried dates from earlier years.

Table: homes in projects the DLD register recorded as completed, by quarter of completion. Source: DLD project register, Peak Trust Research.

Completed Projects Homes
2025 (full year) 74 31,078
Q1 2026 38 15,325
Q2 2026 58 33,499
Q3 2026 56 33,566

Is 2027 the peak?

On the register, 2027 and 2028 are the two biggest years, but most of that supply hasn't left the ground. Of the homes due in 2027, 57,036 were in projects recorded at 0% construction, as were 62,559 of those due in 2028. And 159 projects due in 2027 had not started. The 0% figure counts every project recording no construction, whatever its status. Projects the register lists as not started hold 41,849 of those 2027 homes, the figure our Developer Outlook uses; the other 15,187 are in projects listed as active or pending that have yet to record any construction.

On past delivery rates, a good part of 2027 is likely to move into 2028 and 2029. That flattens the peak without removing it, because the homes still arrive, only later. The register shows schedules stretching. The completion dates filed for projects registered in 2026 sit a median 2.6 years after registration (250 projects), against 2.3 years for 2025 registrations (188) and 2.0 years for 2024 registrations (132).

Where are the handovers?

Table: homes scheduled for completion by area, 2026–2029, the 12 areas with the most. DLD registry names, with the common name where one applies. Source: DLD project register, Peak Trust Research.

Area 2026 2027 2028 2029 Total 2026–2029
Dubai South (Madinat Al Mataar) 7,967 12,465 7,307 7,906 35,645
Jumeirah Village Circle (Al Barsha South Fourth) 9,437 7,070 6,587 3,573 26,667
Wadi Al Safa 5 3,188 7,800 10,968 2,196 24,152
Business Bay 15,229 3,620 1,204 1,451 21,504
Wadi Al Safa 4 0 7,833 4,441 2,868 15,142
Wadi Al Safa 3 2,212 6,699 5,328 362 14,601
Downtown Dubai (Burj Khalifa) 10,496 1,905 80 0 12,481
Dubai Maritime City (Madinat Dubai Almelaheyah) 1,454 1,203 4,077 4,547 11,281
Al Hebiah First 47 3,261 7,215 598 11,121
Dubai Marina (Marsa Dubai) 3,727 3,028 3,414 625 10,794
Dubai Islands (Palm Deira) 1,710 4,234 3,714 1,074 10,732
Dubai Investment Park Second 0 1,880 1,476 6,351 9,707

Timing varies a lot by area. Business Bay and Downtown carry most of their pipeline in 2026: 15,229 and 10,496 homes, in just 12 and 5 projects, so a few very large towers. Those 2026 projects were on average 49% and 59% complete. The Wadi Al Safa areas, Al Hebiah First and Dubai Investment Park peak in 2027–2029, almost entirely in projects that haven't been built yet.

Table: the 10 areas with the most homes scheduled for completion in 2026, with average recorded construction progress per project. Source: DLD project register, Peak Trust Research.

Area Projects Homes Average construction recorded
Business Bay 12 15,229 49%
Downtown Dubai (Burj Khalifa) 5 10,496 59%
Jumeirah Village Circle 43 9,437 51%
Dubai South 21 7,967 47%
Dubai Marina 7 3,727 70%
Palm Jumeirah 8 3,508 70%
Wadi Al Safa 5 15 3,188 62%
Arjan (Al Barshaa South Third) 8 2,937 57%
Al Barshaa South Second 3 2,884 51%
Al Hebiah Fourth 6 2,811 70%

JVC is the opposite case to Business Bay. Its 2026 homes are spread over 43 smaller projects, so they should arrive as a steadier stream rather than in a few large blocks.

How do you read a completion date on the register?

Read the date with the percentage. A 2026 date on a project recorded at 20% will in practice be a 2027 or 2028 completion, because Dubai towers don't go from a fifth built to handover in a few months. The percentage comes from the technical reports RERA asks developers to file, and DLD treats a report as expired after three months, so the figure can lag the site by a quarter.

Count projects as well as homes. Ten thousand homes in five towers behave differently from ten thousand in forty mid-rise buildings. A few large projects slipping together can move an area's whole year.

Expect the later years to fill up. 2029 and 2030 look light because many of the projects that will complete then haven't been registered yet. DLD added 250 projects between January and September 2026, and most filed dates two to three years out. For those years the register is a floor.

What it means for developers

  • Plan against the area's pipeline, not the city's. A 2028 completion in Wadi Al Safa 5 lands in that area's biggest year, with 10,968 homes due. In Downtown, 2028 is almost empty.
  • Assume your competitors' dates will slip as well as your own. With half of 2026's homes already late, some of the supply you hand over against will be last year's schedule. The bunching moves; it doesn't disappear.
  • Unit type matters as much as volume. Several of the biggest pipelines are also studio-heavy areas. Read this alongside our unit-mix guide: a studio completing in Dubai South in 2027 competes with a lot of near-identical stock.
  • Land bought now is unlikely to complete before 2029 or 2030. On today's register those years look thin, at 65,438 and 37,910 homes, but they will fill as more projects register.

For investors

A completion date on the register is a schedule, and it can move. Before buying off-plan, check the project's recorded progress against its date and how many homes are due in the same area in the same year. Set the pipeline against the area's rental yields and rent levels.

Peak Trust advises developers on launch timing against supply. See our work with developers.

Related: Dubai land deals 2023–2026 · Launch Watch: every project DLD registered in 2026

Questions readers ask

How many homes will be handed over in Dubai in 2026?
DLD's register lists 85,375 homes with a 2026 completion date, but a scheduled date is not a delivery. Half of those dates had passed by early October, with the projects about 56% built on average. The register recorded 82,390 homes in 152 projects as completed between January and September 2026, but many of those had dates in earlier years.
Is there an oversupply of property in Dubai in 2027?
The register has 104,339 homes scheduled for 2027 and 107,484 for 2028, its two largest years. But 57,036 of the 2027 homes were at 0% construction in October 2026, so a large share is likely to slip into later years. Whether that adds up to oversupply depends on the area and unit type, not the citywide total.
Which areas have the most handovers coming in Dubai?
Dubai South has the most homes scheduled across 2026–2029 (35,645), followed by Jumeirah Village Circle (26,667), Wadi Al Safa 5 (24,152) and Business Bay (21,504). Business Bay and Downtown Dubai are concentrated in 2026, Wadi Al Safa 4 and 5 in 2027–2028.
Why do handover forecasts differ between sources?
Some count only projects registered with DLD, as this guide does. Others add announced and launched projects that aren't on the register yet, or apply a delivery rate to the schedule, which gives a bigger or a smaller number. Check what each source counts.

Sources

  1. Dubai Land Department (project register), Peak Trust Research, 7 Oct 2026